Informasi AHSP
Harga Total
Rp 1,459,835.00
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.417 | Rp 135,000.00 | Rp 56,295.00 |
| 2 | Tukang pipa | OH | 0.696 | Rp 218,000.00 | Rp 151,728.00 |
| 3 | Kepala tukang | OH | 0.07 | Rp 245,000.00 | Rp 17,150.00 |
| 4 | Mandor | OH | 0.021 | Rp 222,000.00 | Rp 4,662.00 |
| B. Bahan | |||||
| 1 | Pompa booster 150 lpm (vertical in line-packaged) | unit | 1.025 | Rp 1,200,000.00 | Rp 1,230,000.00 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 1,459,835.00
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 1,459,835.00
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 21 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak