Informasi AHSP
Harga Total
Rp 1,066,787.80
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.121 | Rp 135,000.00 | Rp 16,335.00 |
| 2 | Tukang batu | OH | 0.203 | Rp 218,000.00 | Rp 44,254.00 |
| 3 | Kepala tukang | OH | 0.02 | Rp 245,000.00 | Rp 4,900.00 |
| 4 | Mandor | OH | 0.006 | Rp 222,000.00 | Rp 1,332.00 |
| B. Bahan | |||||
| 1 | Galian tanah biasa | M3 | 2 | Rp 45,000.00 | Rp 90,000.00 |
| 2 | Buis beton dia. 80 cm | buah | 2 | Rp 255,400.00 | Rp 510,800.00 |
| 3 | Ijuk | kg | 9 | Rp 7,000.00 | Rp 63,000.00 |
| 4 | Kerikil | m3 | 0.502 | Rp 352,300.00 | Rp 176,854.60 |
| 5 | Beton | m3 | 0.05 | Rp 825,000.00 | Rp 41,250.00 |
| 6 | Tulangan | kg | 5.024 | Rp 10,300.00 | Rp 51,747.20 |
| 7 | Bekisting | m2 | 0.502 | Rp 37,500.00 | Rp 18,825.00 |
| 8 | Pipa PVC D Ø 4" | m | 1.2 | Rp 39,575.00 | Rp 47,490.00 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 1,066,787.80
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 1,066,787.80
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 31 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak