Informasi AHSP
Harga Total
Rp 299,388.00
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.325 | Rp 135,000.00 | Rp 43,875.00 |
| 2 | Tukang kayu | OH | 0.225 | Rp 218,000.00 | Rp 49,050.00 |
| 3 | Kepala tukang | OH | 0.003 | Rp 245,000.00 | Rp 735.00 |
| 4 | Mandor | OH | 0.003 | Rp 222,000.00 | Rp 666.00 |
| 5 | Tukang batu | OH | 0.05 | Rp 218,000.00 | Rp 10,900.00 |
| 6 | Tukang Listrik | OH | 0.044 | Rp 218,000.00 | Rp 9,592.00 |
| B. Bahan | |||||
| 1 | Skirting MDF 15 mm | m1 | 1.05 | Rp 15,000.00 | Rp 15,750.00 |
| 2 | Lem Kayu | kg | 0.05 | Rp 16,400.00 | Rp 820.00 |
| 3 | Stop Kontak 1p 3 gang | buah | 1.1 | Rp 150,000.00 | Rp 165,000.00 |
| C. Peralatan | |||||
| 1 | Linggis (baja keras) | buah | 0.1 | Rp 30,000.00 | Rp 3,000.00 |
Jumlah Harga (A+B+C)
Rp 299,388.00
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 299,388.00
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 31 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak