Informasi AHSP
Harga Total
Rp 1,165,602.44
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OJ | 0.9651 | Rp 135,000.00 | Rp 130,288.50 |
| 2 | Tukang Batu | OJ | 0.2413 | Rp 218,000.00 | Rp 52,603.40 |
| 3 | Mandor | OJ | 0.0483 | Rp 222,000.00 | Rp 10,722.60 |
| B. Bahan | |||||
| 1 | Lantai Kerja fc 10 Mpa | m3 | 0.0665 | Rp 1,236,000.00 | Rp 82,194.00 |
| 2 | Urukan Pasir Uruk | m3 | 0.133 | Rp 488,180.00 | Rp 64,927.94 |
| 3 | U-Ditch 100x100x120 cm | buah | 0.8333 | Rp 570,000.00 | Rp 474,981.00 |
| C. Peralatan | |||||
| 1 | Sewa mobil crane | jam | 0.2413 | Rp 1,450,000.00 | Rp 349,885.00 |
Jumlah Harga (A+B+C)
Rp 1,165,602.44
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 1,165,602.44
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 24 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak