Informasi AHSP
Harga Total
Rp 1,475,077.92
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OJ | 1.2795 | Rp 135,000.00 | Rp 172,732.50 |
| 2 | Tukang Batu | OJ | 0.3199 | Rp 218,000.00 | Rp 69,738.20 |
| 3 | Mandor | OJ | 0.064 | Rp 222,000.00 | Rp 14,208.00 |
| B. Bahan | |||||
| 1 | Lantai Kerja fc 10 Mpa | m3 | 0.0885 | Rp 1,236,000.00 | Rp 109,386.00 |
| 2 | Urukan Pasir Uruk | m3 | 0.1779 | Rp 488,180.00 | Rp 86,847.22 |
| 3 | U-Ditch 140x140x120 cm | buah | 0.8333 | Rp 670,000.00 | Rp 558,311.00 |
| C. Peralatan | |||||
| 1 | Sewa mobil crane | jam | 0.3199 | Rp 1,450,000.00 | Rp 463,855.00 |
Jumlah Harga (A+B+C)
Rp 1,475,077.92
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 1,475,077.92
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 24 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak