Informasi AHSP
Harga Total
Rp 1,674,403.00
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OJ | 1.3649 | Rp 135,000.00 | Rp 184,261.50 |
| 2 | Tukang Batu | OJ | 0.3412 | Rp 218,000.00 | Rp 74,381.60 |
| 3 | Mandor | OJ | 0.0682 | Rp 222,000.00 | Rp 15,140.40 |
| B. Bahan | |||||
| 1 | Lantai Kerja fc 7,5 Mpa | m3 | 0.1125 | Rp 928,000.00 | Rp 104,400.00 |
| 2 | Urukan Pasir Uruk | m3 | 0.225 | Rp 488,180.00 | Rp 109,840.50 |
| 3 | U-Ditch 180x200x120 cm | buah | 0.8333 | Rp 830,000.00 | Rp 691,639.00 |
| C. Peralatan | |||||
| 1 | Sewa mobil crane | jam | 0.3412 | Rp 1,450,000.00 | Rp 494,740.00 |
Jumlah Harga (A+B+C)
Rp 1,674,403.00
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 1,674,403.00
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 24 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak