Informasi AHSP
Harga Total
Rp 298,149.10
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.66 | Rp 135,000.00 | Rp 89,100.00 |
| 2 | Tukang kayu | OH | 0.33 | Rp 218,000.00 | Rp 71,940.00 |
| 3 | Kepala tukang | OH | 0.033 | Rp 245,000.00 | Rp 8,085.00 |
| 4 | Mandor | OH | 0.011 | Rp 222,000.00 | Rp 2,442.00 |
| B. Bahan | |||||
| 1 | Paku 4 inch | kg | 0.4 | Rp 19,000.00 | Rp 7,600.00 |
| 2 | Minyak bekisting | liter | 0.2 | Rp 16,800.00 | Rp 3,360.00 |
| 3 | Kayu balok 6/12 kelas II | m3 | 0.006 | Rp 10,250,000.00 | Rp 61,500.00 |
| 4 | Plywood 12 mm | lembar | 0.127 | Rp 167,300.00 | Rp 21,247.10 |
| 5 | Dolken kayu φ 8-10 panjang 400 cm | batang | 0.975 | Rp 5,000.00 | Rp 4,875.00 |
| 6 | Formtie/penjaga jarak bekesting/spacer | buah | 4 | Rp 7,000.00 | Rp 28,000.00 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 298,149.10
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 298,149.10
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 18 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak