Informasi AHSP
Harga Total
Rp 3,580,449.00
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 3.549 | Rp 135,000.00 | Rp 479,115.00 |
| 2 | Tukang pipa | OH | 0.71 | Rp 218,000.00 | Rp 154,780.00 |
| 3 | Mandor | OH | 0.356 | Rp 222,000.00 | Rp 79,032.00 |
| B. Bahan | |||||
| 1 | Pipa Baja dia. 600 mm | m | 1 | Rp 2,650,000.00 | Rp 2,650,000.00 |
| C. Peralatan | |||||
| 1 | Excavator | Hari | 0.041 | Rp 5,150,000.00 | Rp 211,150.00 |
| 2 | Sewa Tripot | Hari | 0.059 | Rp 108,000.00 | Rp 6,372.00 |
Jumlah Harga (A+B+C)
Rp 3,580,449.00
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 3,580,449.00
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 24 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak