Informasi AHSP
Harga Total
Rp 1,423,545.34
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 1 | Rp 135,000.00 | Rp 135,000.00 |
| 2 | Tukang batu | OH | 0.25 | Rp 218,000.00 | Rp 54,500.00 |
| 3 | Kepala Tukang | OH | 0.025 | Rp 245,000.00 | Rp 6,125.00 |
| 4 | Mandor | OH | 0.1 | Rp 222,000.00 | Rp 22,200.00 |
| B. Bahan | |||||
| 1 | Semen Portland (PC) | kg | 400 | Rp 1,300.00 | Rp 520,000.00 |
| 2 | Pasir beton | kg | 672 | Rp 300.00 | Rp 201,600.00 |
| 3 | Batu split 2/3 | kg | 1440 | Rp 242.97 | Rp 349,870.34 |
| 4 | Strorox-100 | kg | 1.2 | Rp 40,000.00 | Rp 48,000.00 |
| 5 | Air | liter | 210 | Rp 200.00 | Rp 42,000.00 |
| C. Peralatan | |||||
| 1 | Molen beton mixer 350 liter | hari | 0.1475 | Rp 300,000.00 | Rp 44,250.00 |
Jumlah Harga (A+B+C)
Rp 1,423,545.34
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 1,423,545.34
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 31 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak