Informasi AHSP
Harga Total
Rp 606,677.79
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.25 | Rp 135,000.00 | Rp 33,750.00 |
| 2 | Tukang kayu | OH | 0.125 | Rp 218,000.00 | Rp 27,250.00 |
| 3 | Tukang batu | OH | 0.125 | Rp 218,000.00 | Rp 27,250.00 |
| 4 | Kepala tukang | OH | 0.025 | Rp 245,000.00 | Rp 6,125.00 |
| 5 | Mandor | OH | 0.008 | Rp 222,000.00 | Rp 1,776.00 |
| B. Bahan | |||||
| 1 | Kaso 5/7 kayu kelas II | m3 | 0.031 | Rp 10,214,200.00 | Rp 316,640.20 |
| 2 | Seng gelombang | lembar | 1.3125 | Rp 85,000.00 | Rp 111,562.50 |
| 3 | Paku biasa 5 inchi | kg | 0.4271 | Rp 20,000.00 | Rp 8,542.00 |
| 4 | Semen Portland (PC) | kg | 26.406 | Rp 1,300.00 | Rp 34,327.80 |
| 5 | Pasir beton | kg | 61.56 | Rp 300.00 | Rp 18,468.00 |
| 6 | Kerikil | kg | 83.349 | Rp 210.00 | Rp 17,503.29 |
| 7 | Air | liter | 17.415 | Rp 200.00 | Rp 3,483.00 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 606,677.79
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 606,677.79
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 31 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak