Informasi AHSP
Harga Total
Rp 117,272.00
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.18 | Rp 135,000.00 | Rp 24,300.00 |
| 2 | Tukang batu | OH | 0.02 | Rp 218,000.00 | Rp 4,360.00 |
| 3 | Tukang kayu | OH | 0.02 | Rp 218,000.00 | Rp 4,360.00 |
| 4 | Tukang besi | OH | 0.02 | Rp 218,000.00 | Rp 4,360.00 |
| 5 | Kepala tukang | OH | 0.006 | Rp 245,000.00 | Rp 1,470.00 |
| 6 | Mandor | OH | 0.002 | Rp 222,000.00 | Rp 444.00 |
| B. Bahan | |||||
| 1 | Kayu papan kelas III | m3 | 0.002 | Rp 8,000,000.00 | Rp 16,000.00 |
| 2 | Paku 12 cm | kg | 0.01 | Rp 1,500.00 | Rp 15.00 |
| 3 | BjTP | kg | 3 | Rp 14,250.00 | Rp 42,750.00 |
| 4 | Kawat beton | kg | 0.45 | Rp 18,800.00 | Rp 8,460.00 |
| 5 | Semen portland (PC) | kg | 4 | Rp 1,300.00 | Rp 5,200.00 |
| 6 | Pasir beton (quarry - lokasi pekerjaan) | m3 | 0.006 | Rp 370,200.00 | Rp 2,221.20 |
| 7 | Batu split 1/2 | m3 | 0.009 | Rp 370,200.00 | Rp 3,331.80 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 117,272.00
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 117,272.00
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 13 February 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak