Informasi AHSP
Harga Total
Rp 372,199.01
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.308 | Rp 135,000.00 | Rp 41,580.00 |
| 2 | Tukang kayu | OH | 0.154 | Rp 218,000.00 | Rp 33,572.00 |
| 3 | Tukang batu | OH | 0.154 | Rp 218,000.00 | Rp 33,572.00 |
| 4 | Kepala tukang | OH | 0.031 | Rp 245,000.00 | Rp 7,595.00 |
| 5 | Mandor | OH | 0.01 | Rp 222,000.00 | Rp 2,220.00 |
| B. Bahan | |||||
| 1 | Kaso 5/7 kayu kelas II | m3 | 0.0139 | Rp 10,214,200.00 | Rp 141,977.38 |
| 2 | Kawat duri | m' | 20.4457 | Rp 1,750.00 | Rp 35,779.98 |
| 3 | Paku biasa 5 inchi | kg | 0.4715 | Rp 20,000.00 | Rp 9,430.00 |
| 4 | Semen Portland (PC) | kg | 26.406 | Rp 1,300.00 | Rp 34,327.80 |
| 5 | Pasir beton | kg | 83.349 | Rp 300.00 | Rp 25,004.70 |
| 6 | Kerikil | Kg | 17.415 | Rp 210.00 | Rp 3,657.15 |
| 7 | Air | liter | 17.415 | Rp 200.00 | Rp 3,483.00 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 372,199.01
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 372,199.01
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 31 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak