Informasi AHSP
Harga Total
Rp 411,955.00
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.2 | Rp 135,000.00 | Rp 27,000.00 |
| 2 | Tukang besi | OH | 0.1 | Rp 218,000.00 | Rp 21,800.00 |
| 3 | Tukang batu | OH | 0.1 | Rp 218,000.00 | Rp 21,800.00 |
| 4 | Mandor | OH | 0.02 | Rp 222,000.00 | Rp 4,440.00 |
| B. Bahan | |||||
| 1 | Seng gelombang bjls 30 panjang 180 cm | lembar | 1.2 | Rp 73,300.00 | Rp 87,960.00 |
| 2 | Baja L 40.40.4 | kg | 13.5 | Rp 14,840.00 | Rp 200,340.00 |
| 3 | Kawat seng 3mm | kg | 0.3 | Rp 18,800.00 | Rp 5,640.00 |
| 4 | Pasangan batu ukuran 20/50 t=40cm | m3 | 0.15 | Rp 286,500.00 | Rp 42,975.00 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 411,955.00
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 411,955.00
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 31 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak