Informasi AHSP
Harga Total
Rp 75,557.50
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.07 | Rp 135,000.00 | Rp 9,450.00 |
| 2 | Tukang cat | OH | 0.105 | Rp 218,000.00 | Rp 22,890.00 |
| 3 | Kepala tukang | OH | 0.0105 | Rp 245,000.00 | Rp 2,572.50 |
| 4 | Mandor | OH | 0.0035 | Rp 222,000.00 | Rp 777.00 |
| B. Bahan | |||||
| 1 | Meni kayu | kg | 0.2 | Rp 34,500.00 | Rp 6,900.00 |
| 2 | Plamir kayu | kg | 0.15 | Rp 30,100.00 | Rp 4,515.00 |
| 3 | Cat dasar (cat kayu) | kg | 0.17 | Rp 38,200.00 | Rp 6,494.00 |
| 4 | Cat penutup (cat kayu) | kg | 0.35 | Rp 58,500.00 | Rp 20,475.00 |
| 5 | Kuas 3 inch | buah | 0.01 | Rp 10,400.00 | Rp 104.00 |
| 6 | Pengencer cat kayu/besi | kg | 0.03 | Rp 20,000.00 | Rp 600.00 |
| 7 | Amplas | lembar | 0.2 | Rp 3,900.00 | Rp 780.00 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 75,557.50
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 75,557.50
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 19 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak