Informasi AHSP
Harga Total
Rp 4,544,818.00
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.067 | Rp 135,000.00 | Rp 9,045.00 |
| 2 | Tukang tanam | OH | 0.067 | Rp 218,000.00 | Rp 14,606.00 |
| 3 | Mandor | OH | 0.033 | Rp 222,000.00 | Rp 7,326.00 |
| B. Bahan | |||||
| 1 | Pohon Besar Beringin | buah | 1.05 | Rp 2,900,000.00 | Rp 3,045,000.00 |
| 2 | Anti Rayap tanah | kg | 0.02 | Rp 28,500.00 | Rp 570.00 |
| 3 | Bambu panjang 2 meter | batang | 3 | Rp 7,000.00 | Rp 21,000.00 |
| 4 | Tali Ijuk | m | 15 | Rp 200.00 | Rp 3,000.00 |
| 5 | Tanah Subur | m3 | 0.146 | Rp 165,000.00 | Rp 24,090.00 |
| 6 | Pupuk organik | m3 | 0.039 | Rp 178,000.00 | Rp 6,942.00 |
| 7 | kompos | m3 | 0.01 | Rp 165,000.00 | Rp 1,650.00 |
| C. Peralatan | |||||
| 1 | Crane | jam | 0.41 | Rp 3,442,900.00 | Rp 1,411,589.00 |
Jumlah Harga (A+B+C)
Rp 4,544,818.00
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 4,544,818.00
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 19 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak