Informasi AHSP
Harga Total
Rp 164,920.40
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 0.001 | Rp 135,000.00 | Rp 135.00 |
| 2 | Tukang tanam | OH | 0.002 | Rp 218,000.00 | Rp 436.00 |
| 3 | Mandor | OH | 0.0002 | Rp 222,000.00 | Rp 44.40 |
| B. Bahan | |||||
| 1 | Matras Tipe II, Termasuk angkur / penguat matras | m2 | 1 | Rp 7,500.00 | Rp 7,500.00 |
| 2 | Perekat Campuran Hydroseeding | kg | 0.003 | Rp 16,000.00 | Rp 48.00 |
| 3 | Bibit Vegetasi (Biji Legume Crop Cover/LCC) | kg | 0.015 | Rp 166,000.00 | Rp 2,490.00 |
| 4 | Mulsa | kg | 0.3 | Rp 35,000.00 | Rp 10,500.00 |
| 5 | Pupuk Organik | kg | 0.8 | Rp 178,000.00 | Rp 142,400.00 |
| 6 | Pupuk anorganik | kg | 0.004 | Rp 18,000.00 | Rp 72.00 |
| 7 | Air | liter | 5.6 | Rp 200.00 | Rp 1,120.00 |
| C. Peralatan | |||||
| 1 | Sewa Mesin Hydroseeding 2000L | hari | 0.0005 | Rp 350,000.00 | Rp 175.00 |
Jumlah Harga (A+B+C)
Rp 164,920.40
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 164,920.40
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 19 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak