Informasi AHSP
Harga Total
Rp 3,458,195.00
| No | Uraian | Satuan | Koefisien | Harga Satuan | Jumlah Harga |
|---|---|---|---|---|---|
| A. Tenaga Kerja | |||||
| 1 | Pekerja | OH | 2 | Rp 135,000.00 | Rp 270,000.00 |
| 2 | Tukang kayu | OH | 2 | Rp 218,000.00 | Rp 436,000.00 |
| 3 | Tukang batu | OH | 1 | Rp 218,000.00 | Rp 218,000.00 |
| 4 | Kepala tukang | OH | 0.3 | Rp 245,000.00 | Rp 73,500.00 |
| 5 | Mandor | OH | 0.1 | Rp 222,000.00 | Rp 22,200.00 |
| B. Bahan | |||||
| 1 | Dolken kayu φ 8-10 panjang 400 cm | m' | 1.25 | Rp 5,000.00 | Rp 6,250.00 |
| 2 | Kayu | m3 | 0.18 | Rp 11,950,000.00 | Rp 2,151,000.00 |
| 3 | Paku biasa 5 inchi | kg | 0.08 | Rp 20,000.00 | Rp 1,600.00 |
| 4 | Besi strip | kg | 1.1 | Rp 7,500.00 | Rp 8,250.00 |
| 5 | Semen Portland (PC) | kg | 35 | Rp 1,300.00 | Rp 45,500.00 |
| 6 | Pasir pasang | m3 | 0.15 | Rp 200,000.00 | Rp 30,000.00 |
| 7 | Pasir beton | m3 | 0.1 | Rp 300.00 | Rp 30.00 |
| 8 | Koral Beton | m3 | 0.15 | Rp 352,300.00 | Rp 52,845.00 |
| 9 | Bata merah | buah | 30 | Rp 700.00 | Rp 21,000.00 |
| 10 | Seng pelat | lembar | 0.25 | Rp 72,200.00 | Rp 18,050.00 |
| 11 | Jendela nako | buah | 0.2 | Rp 400,000.00 | Rp 80,000.00 |
| 12 | Kaca polos | m2 | 0.08 | Rp 120,000.00 | Rp 9,600.00 |
| 13 | Kunci tanam | buah | 0.15 | Rp 65,800.00 | Rp 9,870.00 |
| 14 | Plywood 4 mm | lembar | 0.06 | Rp 75,000.00 | Rp 4,500.00 |
| C. Peralatan | |||||
| Tidak ada data peralatan. | |||||
Jumlah Harga (A+B+C)
Rp 3,458,195.00
Overhead (0.00%)
Rp 0.00
Harga Satuan Pekerjaan
Rp 3,458,195.00
Informasi Tambahan
- Sumber: Surat Edaran Dirjen Bina Konstruksi No.30 Tahun 2025
- Data terakhir diperbarui: 31 January 2026
- Harga sudah termasuk overhead 0.00%
- Harga belum termasuk pajak